How failed power projects have shackled India's energy growth
Photo Credit: Wikimedia Commons
24.1K
Total Views
Over the last seven years, about 75 projects in the energy sector worth about Rs 70,000 crore, which could have generated 30,809 mega watts (MW) of energy – enough to supply 11% of India’s annual power-generation capacity –were terminated.

As of September this year, the gap between demand and supply is 2.4% (15,981 million units), according to power ministry data. So if the projects were running, India might have had enough energy.

They were stopped because of a range of issues: from getting land and finance to profitability and local issues. Government projects running behind schedule and cost overruns because of bureaucratic snarls appear to be other reasons. Almost 44% of cancelled projects were in Madhya Pradesh, Chhattisgarh and Andhra Pradesh.

Source: Infrastructure India (Department of Economic Affairs) 
The 2005 plan

In its 2005 National Power Policy, the United Progressive Alliance government promised to electrify all villages in the country by 2010 and ensure 1,000 kilowatt-hours (kWh), a measure of electric power, per capita by 2012. The government missed both targets by miles.

The target of 1,000 kWh per capita could be achieved only in 2014-15, and more than 16,000 villages are still living in darkness. As many as 55.8% households were without electricity, according to a 2011 census report.

Source: Rajya Sabha
Demand grows

The termination of energy projects leads to shortage of supply while demand continues to grow, according to Anand S, engineering officer, Central Power Research Institute, Bangalore.

“Many times, these projects remain on paper; they never see the light of the day,” he said.

India is the world’s third-largest consumer, following China and the US, but even with the per capita target of 1,000 kWh met in 2014-15, it is among the lowest in the world, Mint reported. China consumes four times as much power, and the developed nation average is 15 times as much.

Myriad obstacles

“The past policies are unsustainable for our growing population,” said Shankar Sharma, a power policy analyst. “The lack of clarity, stable policies and professionalism, and political interference are major bottlenecks.”

Of the 1,200 power projects launched by the government over the past 40 years, 594 are under construction, including 111 projects that are running behind schedule with a cost overrun of Rs 61,694 crore.

The average cost escalation per project is Rs 550 crore.

Source: Infrastructure India (Dept of Economic Affairs)
Acquisition of land, eviction of people, shortage of manpower, improper management and delays in supplying raw materials are some of the primary reasons for delays, according to power ministry data. There is a major communication gap between the government and people when it comes to executing major power projects, experts said.

“Active participation from various sections of the society in all the important decision-making processes is critical,” Sharma said.

The lack of coordination between the state and central governments also contributes to the hold-up: as many as 47 delayed projects are multi-state projects.

Source: Lok Sabha
The Electricity Act, 2003, mandates central and state electricity regulatory commissions. The Act states that the commissions need to be independent regulatory bodies for proper administration of the power sector.

“In practice, the appointment of the chairman and members of these institutions is done politically,” Singh said.

Queries sent via e-mail to power minister Piyush Goyal, chairman of the Central Electric Regulatory Commission Gireesh B Pradhan, and secretary, Central Electric Regulatory Commission Shubha Sharma did not elicit any response.

Experts believe the government needs to rework its strategy. Instead of maximising electricity production, it should focus on minimum electricity needed to electrify a household in rural areas at the lowest cost, Sharma said.

[“source-scroll”]